Earned Value Management and Agile Processes

I've recently been working with a client whose customer requires project reporting using Earned Valued Management metrics (EVM). It made me realise that, since they are also wishing to use agile methods, a paper I wrote back in 2008 could be relevant to them, and maybe a few others. When I looked for it online it was no longer available, so I thought I'd remedy that here. You can access the paper by clicking this link: EVM and Agile Processes – an investigation of applicability and benefits.

EVM is a technique for showing how closely a project is following both its planned schedule and planned costs. It's a superior method to simply reporting time and cost variance, since if the project has slipped but also underspent you cannot tell from the simple variances the degree to which the underspend has caused the slippage. EVM's cost efficiency and schedule efficiency (nothing to do with efficiency by the way!) can tell you this.

However agile methods do not have a fixed scope during their lifecycle and this can make EVM reporting effectively meaningless. The paper explains a technique for using the substitutability of User Stories, estimated in points, for overcoming this problem. If this is relevant to your business environment, I hope you find it useful.

Agile EVM has continued to develop since this paper and you can find more details and further references in the Wikipedia entry here: Earned value management: Agile EVM.

Citation: Andy Carmichael (2008). EVM and Agile Processes – an investigation of applicability and benefits, The 2nd Earned Value Management Conference, NEC, Birmingham UK, 12 March 2008.
Project Manager Today Events. www.pmtoday.co.uk.
Post a Comment

Popular posts from this blog

Does your Definition of Done allow known defects?

Is it just me or do you also find it odd that some teams have clauses like this in their definition of done (DoD)?
... the Story will contain defects of level 3 severity or less only ... Of course they don't mean you have to put minor bugs in your code - that really would be mad - but it does mean you can sign the Story off as "Done"if the bugs you discover in it are only minor (like spelling mistakes, graphical misalignment, faults with easy workarounds, etc.). I saw DoDs like this some time ago and was seriously puzzled by the madness of it. I was reminded of it again at a meet-up discussion recently - it's clearly a practice that's not uncommon.

Let's look at the consequences of this policy. 

Potentially for every User Story that is signed off as "Done" there could be several additional Defect Stories (of low priority) that will be created. It's possible that finishing a Story (with no additional user requirements) will result in an increase in…

"Plan of Intent" and "Plan of Record"

Ron Lichty is well known in the Software Engineering community on the West Coast as a practitioner, as a seasoned project manager of many successful ventures and in a number of SIGs and conferences in which he is active. In spite of knowing Ron by correspondence over a long period of time it was only at JavaOne this year that we finally got together and I'm very glad we did.

Ron wrote to me after our meeting:

I told a number of people later at JavaOne, and even later that evening at the Software Engineering Management SIG, about xProcess. It really looks good. A question came up: It's a common technique in large organizations to keep a "Plan of Intent" and a "Plan of Record" - to have two project plans, one for the business partners and boss, one you actually execute to. Any support for that in xProcess?

Good question! Here's my reply...

There is support in xProcess for an arbitrary number of target levels through what we call (in the process definitions) P…

Understanding Cost of Delay and its Use in Kanban

Cost of Delay (CoD) is a vital concept to understand in product development. It should be a guide to the ordering of work items, even if - as is often the case - estimating it quantitatively may be difficult or even impossible. Analysing Cost of Delay (even if done qualitatively) is important because it focuses on the business value of work items and how that value changes over time. An understanding of Cost of Delay is essential if you want to maximise the flow of value to your customers.

Don Reinertsen in his book Flow [1] has shown that, if you want to deliver the maximum business value with a given size team, you give the highest priority, not to the most valuable work items in your "pool of ideas," not even to the most urgent items (those whose business value decays at the fastest rate), nor to your smallest items. Rather you should prioritise those items with the highest value of urgency (or CoD) divided by the time taken to implement them. Reinertsen called this appro…