Skip to main content

How long should a Sprint be?

Generally I'd I'd say between 2 and 4 weeks. How long can the business leave the team alone to get on with what they've planned (the "no interruptions"rule) is one constraint. The other is how frequently do we need to update the release plan - we only really get feedback on velocity at sprint boundaries.

I've been working with a team recently where establishing a constant velocity has been very difficult. They are basically dealing with a large backlog of defects from previous iterations where they weren't using an agile process. Until this backlog is cleared it's largely academic how long the sprint is - they still get interrupted with a significant number of urgent defect fix tasks every week. Perhaps going to a weekly sprint, at least until this backlog is effectively cleared would help. That way the defects being worked on in that week would be known, with analysis only being done on new defect reports during the week. The sprint planning for the following week can then re-prioritize the work for the following week. This is an example of where the sprint needs to be short in order to handle rapidly changing priorities. However it also demonstrates the difficulty of trying to apply an agile process when a clear quality baseline has not yet been established.

In other circumstances I favour a longer sprint rather than a short one - at least 3 weeks. It gives the team a chance to establish it rhythm of delivering backlog items without the overheads of sprint planning and retrospectives interrupting.
Post a Comment

Popular posts from this blog

Does your Definition of Done allow known defects?

Is it just me or do you also find it odd that some teams have clauses like this in their definition of done (DoD)?
... the Story will contain defects of level 3 severity or less only ... Of course they don't mean you have to put minor bugs in your code - that really would be mad - but it does mean you can sign the Story off as "Done"if the bugs you discover in it are only minor (like spelling mistakes, graphical misalignment, faults with easy workarounds, etc.). I saw DoDs like this some time ago and was seriously puzzled by the madness of it. I was reminded of it again at a meet-up discussion recently - it's clearly a practice that's not uncommon.

Let's look at the consequences of this policy. 

Potentially for every User Story that is signed off as "Done" there could be several additional Defect Stories (of low priority) that will be created. It's possible that finishing a Story (with no additional user requirements) will result in an increase in…

"Plan of Intent" and "Plan of Record"

Ron Lichty is well known in the Software Engineering community on the West Coast as a practitioner, as a seasoned project manager of many successful ventures and in a number of SIGs and conferences in which he is active. In spite of knowing Ron by correspondence over a long period of time it was only at JavaOne this year that we finally got together and I'm very glad we did.

Ron wrote to me after our meeting:

I told a number of people later at JavaOne, and even later that evening at the Software Engineering Management SIG, about xProcess. It really looks good. A question came up: It's a common technique in large organizations to keep a "Plan of Intent" and a "Plan of Record" - to have two project plans, one for the business partners and boss, one you actually execute to. Any support for that in xProcess?

Good question! Here's my reply...

There is support in xProcess for an arbitrary number of target levels through what we call (in the process definitions) P…

Understanding Cost of Delay and its Use in Kanban

Cost of Delay (CoD) is a vital concept to understand in product development. It should be a guide to the ordering of work items, even if - as is often the case - estimating it quantitatively may be difficult or even impossible. Analysing Cost of Delay (even if done qualitatively) is important because it focuses on the business value of work items and how that value changes over time. An understanding of Cost of Delay is essential if you want to maximise the flow of value to your customers.

Don Reinertsen in his book Flow [1] has shown that, if you want to deliver the maximum business value with a given size team, you give the highest priority, not to the most valuable work items in your "pool of ideas," not even to the most urgent items (those whose business value decays at the fastest rate), nor to your smallest items. Rather you should prioritise those items with the highest value of urgency (or CoD) divided by the time taken to implement them. Reinertsen called this appro…